Queenslander Built
Costs & Budget

Build Under Cost Breakdown: What We Actually Spent

Real figures from our Coorparoo build-under — slab, framing, wet areas, and fit-out — with notes on where costs blew out and where we saved.

Queenslander Built 5 min read

Cost guides for Queenslander projects are hard to find. When we were budgeting ours, the best we could find online were vague estimates from builders who wanted a call before they’d give any figures. So here’s our actual breakdown.

All figures are in Australian dollars (AUD) and reflect 2024–2025 pricing in Brisbane. Your project will differ — but this should give you a realistic starting point.

Project scope

  • 3-bedroom Queenslander, approximately 180m² footprint (upstairs)
  • New ground floor of approximately 160m² (full build-under, not just a small room)
  • Coorparoo, inner Brisbane — reasonable access, no extreme constraints
  • Owner-builder procurement, all trades contracted directly

Raise and subfloor

ItemCost
House raising (including temporary works)$42,000
Structural engineering (raise and subfloor design)$6,500
Subfloor framing and stumps$18,000
Subtotal$66,500

The raise quote came in third-lowest of four we received. Cheapest isn’t always best with raisers — we went mid-range with a contractor who had strong references and had worked with our engineer before.


Slab

ItemCost
Earthworks and excavation$8,400
Termite barrier (physical, perimeter)$3,200
Slab formwork and steel$14,500
Concrete supply and pump$11,800
Subtotal$37,900

We had a waffle pod slab designed. The engineer’s specification drove the cost — it’s a reactive clay site and the reinforcing wasn’t cheap.


Framing

ItemCost
External wall framing (90mm stud)$22,000
Internal wall framing$8,500
Roof (garage and carport, new)$14,000
Subtotal$44,500

We used engineered timber (LVL) for the longer spans. It added cost upfront but simplified the framing and reduced future movement.


Rough-in services

ItemCost
Electrical rough-in (ground floor + upgrade upstairs)$18,500
Plumbing rough-in (new bathroom, laundry, toilet)$14,200
HVAC rough-in (ducted to ground floor)$6,800
Subtotal$39,500

Electrical was the biggest variable. We took the opportunity to bring the upstairs wiring up to current standards at the same time — that added about $5,000 but was absolutely worth it.


External works

ItemCost
Windows and external doors (ground floor)$28,000
External cladding (fibre cement, painted)$12,500
Garage door$3,400
Subtotal$43,900

Windows were a significant cost. We used double-glazed aluminium-framed windows throughout the new ground floor — more than timber alternatives but better thermally and less maintenance.


Insulation and internal linings

ItemCost
Wall and ceiling insulation$7,800
Plasterboard supply and install$22,000
Subtotal$29,800

Fit-out (ground floor)

ItemCost
Bathroom fit-out (tiles, fixtures, vanity)$18,500
Laundry fit-out$4,200
Flooring (polished concrete — ground floor)$8,600
Painting (ground floor, internal)$9,800
Electrical fit-off$7,200
Plumbing fit-off$6,400
Subtotal$54,700

Permits and professional fees

ItemCost
Development approval (DA)$4,200
Building approval$3,800
Owner-builder permit$420
Building certifier (inspections)$3,600
Additional engineering (variations)$2,800
Subtotal$14,820

Total build-under cost

CategoryCost
Raise and subfloor$66,500
Slab$37,900
Framing$44,500
Rough-in services$39,500
External works$43,900
Insulation and linings$29,800
Fit-out$54,700
Permits and fees$14,820
Total$331,620

What blew out

Electrical. We underestimated the cost of the upstairs upgrade. Budget generously for electrical — it’s rarely cheaper than you hope.

Windows. We priced double-glazed early and thought we had it covered. By the time we ordered, lead times had extended and one supplier had repriced. Shop early and lock in pricing.

Variations on the slab. When the excavation went deeper than expected in one corner (old fill material), the engineer specified additional reinforcing. That cost about $2,200 extra and wasn’t in the original quote.

Where we saved

Owner-builder procurement. Managing the trades ourselves added time and stress, but it saved meaningful money compared to a builder’s margin. We estimate 15–20% off what a fixed-price contract would have been.

Timing our concreter. We booked three months in advance and got a better rate than the spot price at the time we poured.

Polished concrete instead of flooring. Fewer trades, no moisture barrier issues, and genuinely good-looking.

Filed under

costs budget build-under slab framing

Free download

Want the full cost spreadsheet?

Get the Owner-Builder Build-Under Budget Tracker — every line item from our Coorparoo project, formatted so you can adapt it for yours.

Get the checklist

Subscribers also receive new articles as the build progresses. Unsubscribe any time. No third parties.

More from Queenslander Built

Raising

Raising a Queenslander: What to Expect

From the first quote to the day the house lands on its new stumps — a practical guide to what a Queenslander raise actually involves.

3 min read