Planning

Where renovation budgets blow out

The line items that ran over on our project and the systemic reasons they run over on most projects.

Weatherproofing stage on a Queenslander build-under

1. Electrical

Electrical is the line item most likely to run over. The upstairs board, the tail-end load on existing circuits and the upgrade scope discovered mid-build all add to the original estimate. On the Coorparoo project the electrical upgrade scope cost roughly $5,000 over the original allowance.

2. Windows and glazing

Window prices move and lead times can push out the weatherproofing schedule, so lock the spec and pay the deposit before the slab is poured. A confirmed order early protects both the price and the delivery date.

3. Engineering variations

Variations to engineering scope mid-build are common, so plan for them from the start. Variable ground conditions, a certifier flagging additional bracing or tie-down and scope added to the slab all drive extra cost, which is why a contingency of 5-10% of the structural category is worth holding for variation.

4. External works

External works cover the driveway, pathways, fencing and landscaping, and they are often deferred or left out of the original budget entirely. On the Coorparoo project external works came to $44,250.

5. The 15-20% contingency rule

Budget contingency above your project envelope, and treat 15% as the minimum on a Queenslander build-under. Push it to 20% if you are working with variable ground conditions or significant heritage constraints. Contingencies that are too thin are the single biggest mistake in owner-builder planning, because there is no slack left when the first variation lands.

Tools

Use the Renovation Budget System to model contingency at the line-item level rather than as a single global percentage.

Related

Last updated: May 2026.
The completed Coorparoo Queenslander
How the Coorparoo raise and build-under turned out.

Don't budget by guess

Renovation Budget System - $79

The Coorparoo line items pre-loaded as a worked example. Drop your current quotes alongside and contingency at line level catches blowouts before they happen.

Buy the Budget Toolkit - $79