Planning

Where renovation budgets blow out

The line items that ran over on our project and the systemic reasons they run over on most projects.

Weatherproofing stage on a Queenslander build-under

1. Electrical

Electrical is the line item most likely to come in over. The upstairs board, the tail-end load on existing circuits and the upgrade scope discovered mid-build all add up. On the Coorparoo project the electrical upgrade scope cost us roughly $5,000 over original.

2. Windows and glazing

Window prices move and lead times can blow your weatherproofing schedule. Lock the spec and the deposit before slab is poured.

3. Engineering variations

Variations to engineering scope mid-build are common. Variable ground conditions, a certifier flagging additional bracing or tie-down, scope additions in the slab. Budget 5-10% of structural category for variation contingency.

4. External works

Driveway, pathways, fencing, landscaping. Often deferred and often forgotten in the original budget. On the Coorparoo project external works were $44,250.

5. The 15-20% contingency rule

Budget contingency above your project envelope. Not 5%. Not 10%. 15% is the minimum on a Queenslander build-under; 20% if you're working with variable ground conditions or significant heritage constraints. This is the single biggest mistake we see in owner-builder planning: contingencies that are too thin.

Tools

Use the Renovation Budget System to model contingency at the line-item level rather than as a single global percentage.

Related

Last updated: May 2026.
The completed Coorparoo Queenslander
How the Coorparoo raise and build-under turned out.

Don't budget by guess

Renovation Budget System — $79

The Coorparoo line items pre-loaded as a worked example. Drop your current quotes alongside, and contingency at line level catches blowouts before they happen.

Buy the Budget Toolkit — $79

Or get the free Budget Tracker →