Planning

Sequencing a Queenslander renovation

The order matters more than the speed, because each trade depends on the one before it and certifier inspections gate the whole build.

Framing stage during a Queenslander build-under

The 8 stages

  1. Engineer, certifier, council approvals, owner-builder permit
  2. Site prep, demolition, raise and temporary works
  3. Slab and structural subfloor
  4. Frame, roof and external cladding (weatherproofing milestone)
  5. Services rough-in (electrical, plumbing, gas)
  6. Insulation, plasterboard, paint preparation
  7. Fit-off: cabinetry, fixtures, flooring, paint
  8. Final inspections, certifier sign-off, occupancy

The hold-point sequence

Mandatory certifier inspections sit between the stages at slab, frame, pre-line and final. Each inspection gates the next trade, so missing one delays the build by a week at minimum because trades book out well ahead.

Lead times that bite

  • Windows: 6-10 weeks from confirmed order
  • Engineered timber: 4-6 weeks
  • Certifier inspections: book one week ahead, sometimes two
  • Utility disconnects (raise): 4-6 weeks notice required

The mistake we made

The costliest sequencing mistake was bringing trades on site a day early, on the assumption the certifier would inspect promptly. They did not, so the trades sat idle. Book the certifier first and build the trade calendar around their availability, not the other way around.

Tools

Use the Project Control System to lay your specific sequence against your trades' availability and the certifier's booking window.

Related

Last updated: May 2026.
The completed Coorparoo Queenslander
How the Coorparoo raise and build-under turned out.

Control the sequence

Project Control System - $149

Inspection checklists, hold-point logs, trade contract template, payment tracker, defects log. Everything the day-to-day of the project needs.

Buy the Control Pack - $149

Or see the project timeline →