Queenslander Raise and Build-Under Timeline: From Planning to Fit-Out
How long each stage actually takes: based on a real Coorparoo owner-builder project completed between 2018 and 2020. Stage durations are a reference, not a fixed schedule. Your timeline will depend on council processing times, certifier availability, trade scheduling and site conditions. Brisbane lead times have shifted since this project ran; treat the durations below as illustrative.
These are approximate, project-specific timeframes. Your timeline will depend on council processing times, certifier availability, trade scheduling and site conditions.
Planning & approvals
3-9 months
Raise
18-25 days
Slab
3-5 weeks
Framing + rough-in
6-12 weeks
Linings + fit-out
10-18 weeks
Final + OC
2-4 weeks
Stage by stage
Pre-start
Planning, feasibility and approvals
The longest, most underestimated stage. Includes: structural engineer feasibility assessment, development approval (DA) application and assessment by Brisbane City Council, QBCC owner-builder permit application and course, private certifier engagement and building permit. All of this must be in place before any site works commence.
- DA assessment alone can take 4-10 weeks: sometimes longer
- Start the QBCC owner-builder course and application early; it runs in parallel
- Engage your structural engineer before the DA, not after
Raise
Pre-raise preparation
Services disconnection (water, gas, electrical) by licensed trades, temporary bracing of internal walls if required, access clearances on site. The raiser needs clear access under and around the house for the jack positions. Services must be properly isolated before the house moves.
- Have your plumber and electrician on site the day before raise day
- Clear anything that needs to come out of the subfloor space before it's inaccessible
Raise
Raise day
2018: completed in one day
The contractor sets jack positions, does a test lift, then raises the house in increments: typically 100mm per cycle. A 3.35 m raise takes approximately 8-10 hours from first jacks in to the house at full height. Nobody goes inside once the house is off its stumps.
- Our raise reached full height (3.35 m) in one day
- Expect timber movement and cracking: this is normal in an old Queenslander
- Access to the house ceases once it leaves its stumps
Raise
Temporary supports and permanent subfloor
18 days total (our project)
Once at height, the house sits on temporary steel and timber crib supports while the permanent new subfloor (bearers, joists, stumps) is installed underneath. Hold points apply: the certifier must inspect the subfloor before the house is lowered. Our total from first jacks in to services reconnected was 18 days.
- Daily crib stack checks are the owner-builder's responsibility during this period
- No other trades can work under the house while it's suspended
- Certifier sign-off required before lowering
Build-under
Slab
Earthworks and bulk fill (if required), compaction, termite barrier installation (physical perimeter), reinforcing steel placement, formwork, concrete pour and cure. On a shale site with active ground like ours, the engineer's specification for the raft slab and reinforcing drove cost and schedule.
- Slab reinforcing hold point: certifier inspects before pour
- Allow cure time before loading the slab: typically 28 days to full strength
- Termite barrier installation is a separate item from the slab contractor
Build-under
Framing
External wall framing (ground floor perimeter and any internal load-bearing walls), internal partition framing and any new roof sections (garage, carport). Frame inspection hold point before any lining work commences.
- Frame inspection: certifier checks sizes, bracing, tie-downs and connections
- LVL (engineered timber) for longer spans simplifies framing and reduces future movement
- External cladding typically follows framing but can overlap with rough-in
Build-under
Rough-in services
Electrical rough-in, plumbing rough-in. All must be in before plasterboard. Sequencing matters: electrical and plumbing contractors often need to coordinate over the same wall cavities and floor penetrations. Compliance certificates from each licensed trade are required before the certifier signs off.
- Rough-in hold point: certifier inspects + collects compliance certs before wall closure
- This stage is where sequencing failures most often cause delays
Build-under
Insulation, windows and external cladding
Wall and ceiling insulation, plasterboard delivery prep, window installation and external cladding. Pre-lining inspection before plasterboard is installed. Wet area waterproofing membranes must be in place and signed off before tiling.
- Pre-lining inspection: insulation continuity and wet area waterproofing
- Windows should be ordered months in advance: lead times are long
- Cladding and windows can run in parallel with services rough-in
Build-under
Linings, fit-out and finishes
Plasterboard (supply, hang, set, sand), bathroom tiling and fit-out, laundry fit-out, flooring, painting, electrical fit-off, plumbing fit-off. Each trade works in sequence: plaster before paint, tiles before vanity, flooring before skirting.
- Fit-out is the most complex stage for trade sequencing
- Polished concrete (if used) needs to be poured, cured and ground before other floor finishes
- This stage determines the quality of the finished product: don't rush it
Completion
Final inspection and occupancy certificate
Certifier conducts the final inspection: all trades complete, compliance certs in hand, site clean and safe. The certifier issues the Form 21 (certificate of classification), which is required before the space can be legally occupied. Allow time for any defects identified at final inspection to be rectified.
- Prepare a defects list before the final inspection to address obvious items
- The Form 21 is a permanent document: keep it with your title documents
- Owner-builder resale restrictions begin from the date of Form 21
Key lesson from this project
Planning takes longer than the raise itself.
The approval phase: DA, building permit, QBCC permit, structural engineering documentation: routinely takes 3-6 months. Most people underestimate this stage. Start the QBCC course and council enquiries as early as possible. Don't assume you can start on site in a few weeks.
Key lesson from this project
Confirm what is and is not included in your purchase
If you bought the house from a developer or vendor who described work as “included”: a raise, a subfloor, services, anything structural: get it in writing before you commit to a budget. Verbal inclusions are the most expensive surprises in this kind of project.
Next step
Download the build-under budget tracker
Now you understand the timeline: plan the costs. Get the full $331,510 Coorparoo cost breakdown as a working spreadsheet, free for subscribers.